Given only a Hand Sketch of a rough and a limited footprint of 14’x30’, using our rapid project execution process, we were able to size and procure a centrifugal pump, pressure vessel and 2 plate and frame heat exchangers/ layout on a skid to minimize real estate staying within the footprint, and a create a single 3D Model for fabrication within 3 weeks. The skid was fabricated, equipment, instrumentation and piping was installed and tested tested in the shop, and delivered to the site in a remarkable 5 weeks. The skid unit was in operations 6weeks after receipt of the paper sketch.